The listing below provides advance notice of pending changes to the Market Rules, Market Manuals, technical interfaces or other items that define the operation of the IESO-administered market. For changes that are minor, the listing will identify the document that is changing and a description of the changes, but a link to the altered document may not be included. Comments regarding implementation concerns can be sent to pending.changes@IESO.ca. Details of the market rule process are provided at the Market Rule Amendment process.

Details of all of the documents being revised for this baseline are available in the current Baseline Plan.

Document Type:
Item Last
Updated
Comments
Due
Target
Implementation
Stakeholder
Engagement
 
CNF-MP_ST-P-F_20080831_v1.txt 5-Nov-2008 N/A Baseline 20.1  
This technical document relates to change item A660 - Charge Types for the Settlement of Reactive and Voltage Support Contracts - in the IT release plan for release 20.1.
 
CNF-MP_ST-P-P_20080831.txt 5-Nov-2008 N/A Baseline 20.1  
This technical document relates to change item A660 - Charge Types for the Settlement of Reactive and Voltage Support Contracts - in the IT release plan for release 20.1.
 
Market Manual 5: Settlements Part 5.5: Physical Markets Settlement Statements MDP_PRO_0033 v32.2 29-Oct-2008 7-Nov-2008 Baseline 20.1  
This market manual was revised to add clarification to the description of Administrative Pricing Events related to charge types and the publication of adjustments following the processing of a NOD. Appendix C describes charge types in effect prior to April 1, 2005. The table was erroneously updated with current charge types. Those charges have been removed. A note has been added to describe the intent of the table.
 
IMO_FORM_1546 HADL Offer Submission 22-Oct-2008 N/A Baseline 20.1  
This form is now obsolete due to the termination of the HADL Program and will be removed from the Rules and Manuals page of the IESO public web concurrent with Baseline 20.1.
 
IMO_FORM_1547 Application for Registering as Hour Ahead Dispatchable Load 22-Oct-2008 N/A Baseline 20.1  
This form is now obsolete due to the termination of the HADL Program and will be removed from the Rules and Manuals page of the IESO public web concurrent with Baseline 20.1.
 
IMO_PRO_0105 Market Manual 5.10 Transitional Demand Response Program 22-Oct-2008 N/A Baseline 20.1  
This manual is now obsolete due to the termination of the HADL Program and will be removed from the Rules and Manuals page of the IESO public web concurrent with Baseline 20.1.
 
Market Manual 3: Metering Part 3.10: Transmission Grid - High Voltage Metering IESO_PRO_0573 v0.1 21-Oct-2008 7-Nov-2008 Baseline 20.1  
This new Market Manual is the result of MR-00342: Revision to Ch.6, S2.1.1.1 requirements for Metering Installations. This rule amendment permits a single metering installation for more than one connection point or embedded connection point. There is a new obligation on metered market participants (MMPs) installing these revenue metering installations to review associated information and calculations on an annual basis and when material changes occur.
 
Format Specifications for Settlement Statement Files and Data Files IMP_SPEC_0005 v22.1 21-Oct-2008 7-Nov-2008 Baseline 20.1  
The settlement of the Reactive Support and Voltage Control will be implemented in the Commercial Reconciliation System (CRS). Therefore, charge type 452 has been changed to a monthly uplift for Reactive Support and Voltage Control Settlement. As result of the introduction of a monthly uplift, the sections indicated have been changed to refer to 'Uplifts' rather than 'Hourly Uplift' as previously defined. Added charge types 451, 452, 1401, 1402, 1403, 1404, 1405, 1406, 1407, 1408, 1409 and 1451 for Reactive Support and Voltage Control. Removed charge types 132 and 182 from table 2-5. As a result, of the winding down of the Hour Ahead Dispatchable Load (HADL) program.
 
Outbound Automated Document API IMO_SPEC_0100 v4.1 21-Oct-2008 7-Nov-2008 Baseline 20.1  
Added suggestions on how market participants may increase the efficiency of their scraper processes. Updated the document based on Participant feedback.
 
Market Manual 7.5 -Reliability Information Catalogue IMP_CAT_0001 13.1 21-Oct-2008 7-Nov-2008 Baseline 20.1  
Removed references to Hour Ahead Dispatchable Load (HADL) Program.
 
Market Manual 4.3 - Real-Time Scheduling of the Physical Markets IMP_PRO_0034 27.1 21-Oct-2008 7-Nov-2008 Baseline 20.1  
Due to the termination of the Hour Ahead Dispatchable Load Program all references to the program have been removed from this document.
 
Market Manual 1.2: Facility Registration, Maintenance & Deregistration MDP_PRO_0016 22.1 21-Oct-2008 7-Nov-2008 Baseline 20.1  
Due to the termination of the Hour Ahead Dispatchable Load Program all references to the program have been removed from this document.
 
Market Manual 2.6 - Treatment of Compliance Issues MDP_PRO_0022 15.1 21-Oct-2008 7-Nov-2008 Baseline 20.1  
Due to the termination of the Hour Ahead Dispatchable Load Program all references to the program have been removed from this document.
 
Market Manual 4.2 - Submission of Dispatch Data in the Real-Time Energy and Operating Reserve Markets MDP_PRO_0027 32.1 21-Oct-2008 7-Nov-2008 Baseline 20.1  
Due to the termination of the Hour Ahead Dispatchable Load Program all references to the program have been removed from this document.
 
GST Guide for IESO Transactions IMO_GDE_0002 15.1 21-Oct-2008 7-Nov-2008 Baseline 20.1  
Due to the termination of the Hour Ahead Dispatchable Load Program all references to the program have been removed from this document. In addition there are minor changes to Reactive Support and Voltange Control program - deleted Charge Type 1452, added 'monthly' to CT# 451 name
 
IMO_FORM_1276 IESO System Access and Identity Management Form 21-Oct-2008 7-Nov-2008 Baseline 20.1  
Part 4a of this form referencing 'Submit Global Adjustment Form 1650' had been removed. The form was converted to On-line data submission.
 
MR-00346 - Eliminate the Hour-Ahead Dispatchable Load Program - Definitions 19-Sep-2008 N/A December 10, 2008  
It is proposed to eliminate the Hour-Ahead Dispatchable Load (HADL) program for the following reasons: 1. The program is no longer in use. 2. With the advent of the Ontario Power Authority (OPA) Demand Response 1 (DR1) program, HADL has become redundant; 3. To eliminate IESO costs to maintain the settlement systems and processes to support the program. To effect the elimination of the HADL program, all market rule references to the program would be deleted.
 
MR-00343 - Market Administration - Clarify Recourse Mechanisms for Market Manuals 10-Sep-2008 N/A December 10, 2008  
This amendment proposes changes to the dispute resolution market rules (Chapter 3, section 2.2.1.1) to clarify that the market rule provisions regarding dispute resolution apply to disputes between market participants and the IESO over provisions in market manuals. The need for this clarification was identified by Ontario Power Generation and would add additional transparency to the market rules regarding the application of dispute resolution refer to R00. This amendment also proposes to add the defined term "market manual" wherever the existing market rules contain the phrase "any standard, policy or procedure established by the IESO pursuant to the these market rules" to make it explicit that the relevant provisions apply to market manuals - refer to R00, R01 and R02.
 
 