Related Information Contact Us Connection Assessments and Approvals (CAA)Introduction
In accordance with the Market Rules, Chapter 4, Section 6, anyone planning to construct a new or modified connection to the IESO-controlled grid is required to apply to the IESO and complete the Connection Assessment and Approval (CAA) process. A new or modified connection to the IESO-controlled grid includes:
Detailed information of the CAA process is available in Market Manual 2.10 - Connection Assessment and Approval. The Connection Assessment and Approval process allows the IESO to assess the impact of new or modified connections on the reliability of the integrated power system. A connection applicant does not have to be a Market Participant in order to apply for Connection Assessment and Approval; however, the required participant authorization and facility registration processes must be completed prior to participation in the IESO-administered markets. Assessment and Approval
Obtaining an Assessment provides an overview of the connection process, from submitting an application through to gaining approval. It includes the relevant forms and procedures.
Each project list contains status information for assessments and links to completed SIA reports. |
|||
| Copyright © 2008 Independent Electricity System Operator | ||||