Wind Power Integration in Ontario (SE-29)
As a result of a number of initiatives to increase renewable energy generation supply in the province, particularly wind power generation, the IESO is seeking stakeholder feedback to:
- Better understand the challenges wind power project proponents face in becoming operational in the Ontario market,
- Assist in reducing barriers to participation in the Ontario market,
- Suggest wind power forecasting options or alternatives.
A working group is being created for those with a special focus on wind generation and would like to be actively engaged in working with the IESO to facilitate the integration of wind power in Ontario.
The working sessions and proposed activities listed below deal with the short issues identified by the working group. The schedule of activities for long term issues will be communicated at a later date.
Please note:
Wind issues are being discussed at the Wind Power Integration in Ontario Standing Committee.
Stakeholder Engagement Plan
Working Group
Terms of Reference (Final)
Working Sessions and Proposed Activities
Date Agenda/Minutes |
Supporting Material |
| December 21, 2007 |
Stakeholder Feedback
Summary of Final Evaluation of Stakeholder Effectiveness
|
November 16, 2007
Agenda (Revised)
Minutes (Approved)
|
Working Group meeting #5
Item 2: Administration
2008 Proposed Meeting Dates
Item 3: Next Steps and Ongoing Action Items
Item 4: Wind Forecast Methodology: Approach and Results
Item 5: Mid-term Wind Forecasting Requirements and Options
Item 6: Near-term Wind Forecasting Requirements and Options (Revised)
Stakeholder Feedback
Summary of Session Feedback
Tom Adams
Robert Cary & Associates Inc.
IESO Response to Stakeholder Feedback
|
August 20, 2007
Agenda (Revised)
Minutes (Approved)
|
Working Group meeting #4 to discuss short-term recommendations.
Item 4: Near-term Wind Power Forecasting Analysis (Revised)
Item 5: Recommendations on Short Term Issues
Presentation
Item 6: Compliance requirements for intermittent generators
Stakeholder Feedback
Summary of Session Feedback
|
May 10, 2007
Agenda
Minutes (Approved)
|
Working Group meeting #3 to finalize short term issues recommendations and to discuss some of the long term issues
Item 3: Overview of CanWEA/AWEA 2007 Calgary Conference
Item 4: Distribution System Code Requirements - Embedded Generation
Item 5: Impact of Market and System Operation on Non Dispatchable Generation
Item 6: Wind Performance Testing
Item 7: World-Wide Review of Forecast Methodologies
Stakeholder Feedback
CANWEA
OPG
WINDRUSH
Summary of Session Feedback
|
| March 23, 2007 |
Posting of meeting minutes and action items from Meeting #2 |
March 8, 2007
Agenda (Revised)
Minutes (Approved)
|
Working Group meeting #2: Discuss high priority short term issues
Item 3: Real-Time and Near Term Forecasting Requirements
Item 4: Connection Assessment Requirements
Item 5 & 6: Market Entry Requirements and Operational Control
Stakeholder Feedback
Summary of Session Feedback
|
| January 8, 2007 |
Deadline for comments on issues list |
| December 21, 2006 |
Posting of the draft issues list incorporating stakeholder feedback
Issues List
|
November 27, 2006
Agenda (Revised)
Minutes (Approved)
|
Working Group Meeting #1: Identification and review of wind issues that are highest priority based on the priority rankings.
Describe potential solutions and present proposed schedule for development of solutions.
Determine a schedule for addressing remaining issues.
Item 4: Overview of Ontario Wind Integration Study by GE
Item 5: Integrating Wind Power: Operational Experience
Item 6: Issues List
Additional Issues
WestWindeau Incorporated (1)
WestWindeau Incorporated (2)
Stakeholder Feedback
Summary of Session Feedback
|
| Mid October, 2006 |
Announcement of members of the Working Group
Request for:
Identification of issues that may be barriers to wind power integration; and
Listing of the relative priority of issues where more than one is identified.
|
| September 27, 2006 |
Posting of Stakeholder Engagement Plan.
Nominations for membership in the Wind Issues Working Group;
|
|
| |