Public Policy Considerations of the Treatment of Efficiency and Consumer Impacts in Cost Benefit Analysis (SE-77)

A Cost Benefit Analysis (CBA) is conducted to assess the economic efficiency impacts and reliability impacts of a proposed policy change or project decision.  By quantifying all costs and benefits in monetary terms, it is possible to determine the net benefits (costs) of an option in today’s dollars.   CBA may not take into account all factors that bear on the social benefits of a project.

A paper will be produced which will provide an explanation of how distributional issues can be factored into a CBA and how efficiency improvements can ultimately affect consumers.

The IESO is seeking stakeholder input on what is the appropriate decision criterion to apply when comparing the costs and benefits of proposed changes to market rules, market procedures, or market design.

This stakeholder plan has been developed to define the opportunity for stakeholder involvement in the appropriate CBA decision criteria to apply to proposed changes.

Stakeholder Plan
Stakeholder Plan (Revised, December 11, 2008)
Stakeholder Plan (Revised, February 18, 2009)


Proposed Activities
Date
Agenda/Minutes
Supporting Material Expected Actions
March 10, 2009 Final Evaluation of Stakeholder Engagement Effectiveness  
February 4, 2009 Final outcome – Stakeholder Advisory Committee meeting Final outcome
December 18, 2008 Deadline for additional stakeholder input
• APPrO
Deliberation – Stakeholders to provide input
December 3, 2008 Feedback from Stakeholder Advisory Committee members Deliberation – Stakeholders to provide input
December 2, 2008 Presentation made to Market Pricing Working Group Dialogue – stakeholder input
November 27, 2008 Posting of revised stakeholder plan incorporating feedback from stakeholders
• No comments received
Dialogue – IESO to gather feedback from stakeholders
November 27, 2008 IESO to provide written response to comments on appropriate decision criteria and to post updated discussion paper
Towards the Choice of an IESO Decision Criterion
IESO Response to Stakeholder Comments
IESO to post written response to comments
November 20, 2008 Deadline for written input from stakeholders on the stakeholder plan
• No comments received
IESO to post feedback from stakeholders
November 13, 2008 Deadline for stakeholders to provide written position on appropriate decision criteria
Stakeholder Feedback
John Witjes
  Representing Public Service Consumers
Julie Girvan
  Representing Residential Consumers
Mike Humphries
  Representing Embedded Industrial Customers
Ontario Power Generation
RJ Hunt Management Services Limited
Gary Wight
  Representing Brokers/Marketers
Dialogue - IESO to post feedback from stakeholders
November 6, 2008 Post and communicate stakeholder engagement plan
Stakeholders to provide written feedback. 
October 30, 2008 Discussions with the Stakeholder Advisory Committee regarding the appropriate decision criteria in cost benefit analysis Dialogue – stakeholder input
October 29, 2008 Discussions with the Market Pricing Working Group regarding the appropriate decision criteria in cost benefit analysis Dialogue – stakeholder input
October 20, 2008 Post discussion paper on public policy issue of market efficiency and cost benefit analysis decision criteria
• Discussion paper
IESO to publish discussion paper
 